Please find below the intended construction activities to the end of September 2023. Due to the complexity and duration of this construction project dates are subject to change and this information is provide an indication of our forthcoming activities. Any updates will be captured within the Air Products Project website detailed above and included within the next Quarterly Notification of Continued Construction Works to be distributed in September 2023.
Month | Activities |
---|---|
April 2023 |
Foundation works continue Underground drainage works commence Entrance road widening works completed |
May 2023 |
Foundation works continue Crane Erection / rental period of critical crane (including weekend works on 06th / 07th May and 20th / 21st May) Mobilisation of ME&I Contractor for Cold Box Dressing Structural steel erection commences Critical equipment deliveries |
June 2023 |
Foundation works continue Structural steel erection continues Piping installation commences Electrical & Instrumentation installation commences Critical equipment installation Critical crane demobilised from site Civil roadways and site finishing |
July 2023 |
Foundation works continue Structural steel erection continues Piping installation continues Electrical & Instrumentation installation continues Installation of cooling towers commences Civil roadways and site finishing continues |
August 2023 |
Installation of compressors commences Equipment installation continues Piping installation continues Electrical & Instrumentation installation continues Civil roadways and site finishing continues |
September 2023 |
Installation of compressors commences Equipment installation continues Piping installation continues Electrical & Instrumentation installation continues Civil roadways / site finishing and landscaping continues |